Problem: The Severn Trent Water Authority required a bespoke lifting solution for their water treatment service. The lifting equipment had to work with existing steel infrastructure to lift heavy pumps weighing 1.5 T.
Solution: Lifting & Access designed, manufactured and installed an overhead service crane, more commonly known as a 'semi-goliath'. Lifting & Access proved yet again that they could design around the Seven Trent Water Authority's existing infrastructure to provide a cost effective and fast solution.
Link: www.stwater.co.uk